1
00:00:00,480 --> 00:00:01,320
In this lesson,

2
00:00:01,320 --> 00:00:04,620
we will discuss qualitative risk analysis.

3
00:00:04,620 --> 00:00:08,340
Qualitative risk analysis is one of the primary methods used

4
00:00:08,340 --> 00:00:09,420
in risk management.

5
00:00:09,420 --> 00:00:13,080
So let's dive into the concept of qualitative risk analysis

6
00:00:13,080 --> 00:00:15,810
and its key components of the likelihood,

7
00:00:15,810 --> 00:00:18,510
probability and impact of a given risk.

8
00:00:18,510 --> 00:00:21,060
So what is qualitative risk analysis?

9
00:00:21,060 --> 00:00:23,100
Qualitative risk analysis is a method

10
00:00:23,100 --> 00:00:26,370
of assessing risk based on the potential impact

11
00:00:26,370 --> 00:00:28,620
and likelihood of their occurrence.

12
00:00:28,620 --> 00:00:32,220
It involves categorizing risk as high, medium, or low based

13
00:00:32,220 --> 00:00:35,340
on the potential effect of the project objectives.

14
00:00:35,340 --> 00:00:38,640
Now, this method is subjective and relies on the expertise

15
00:00:38,640 --> 00:00:41,280
and experience of the project team and stakeholders,

16
00:00:41,280 --> 00:00:43,740
and it also avoids the complexity

17
00:00:43,740 --> 00:00:45,780
of the quantitative approach.

18
00:00:45,780 --> 00:00:49,230
Now in the context of qualitative risk analysis,

19
00:00:49,230 --> 00:00:51,240
likelihood and probability refer

20
00:00:51,240 --> 00:00:54,030
to the chance of a particular risk occurring.

21
00:00:54,030 --> 00:00:56,220
It is usually expressed qualitatively

22
00:00:56,220 --> 00:00:58,710
as low, medium or high.

23
00:00:58,710 --> 00:01:00,960
The likelihood of a risk is determined based

24
00:01:00,960 --> 00:01:03,570
on past experience, statistical analysis

25
00:01:03,570 --> 00:01:05,519
or expert judgment.

26
00:01:05,519 --> 00:01:07,200
The impact on the other hand,

27
00:01:07,200 --> 00:01:09,030
refers to the potential consequences

28
00:01:09,030 --> 00:01:10,830
if the risk materializes.

29
00:01:10,830 --> 00:01:13,710
The impact could be in terms of cost, time, quality

30
00:01:13,710 --> 00:01:16,470
of other critical project objectives.

31
00:01:16,470 --> 00:01:19,410
Like likelihood, impact also typically

32
00:01:19,410 --> 00:01:24,060
is rated qualitatively as low, medium, or high.

33
00:01:24,060 --> 00:01:26,370
The impact of a risk is assessed based

34
00:01:26,370 --> 00:01:28,740
on the potential damage it could cause

35
00:01:28,740 --> 00:01:31,110
to the project or business operation.

36
00:01:31,110 --> 00:01:34,110
A low impact means that there is minor damage or loss

37
00:01:34,110 --> 00:01:36,930
and essential functions are still operational.

38
00:01:36,930 --> 00:01:39,300
A moderate or medium impact means there is

39
00:01:39,300 --> 00:01:42,450
a significant damage or loss to assets.

40
00:01:42,450 --> 00:01:44,910
A high impact means there is some major damage

41
00:01:44,910 --> 00:01:47,460
and essential functions cannot be performed.

42
00:01:47,460 --> 00:01:50,130
For example, in a software development project,

43
00:01:50,130 --> 00:01:52,380
one potential risk could be the possibility

44
00:01:52,380 --> 00:01:55,650
of a key team member leaving during the project.

45
00:01:55,650 --> 00:01:57,780
The likelihood of this risk could be assessed

46
00:01:57,780 --> 00:02:01,080
as medium risk considering industry turnover rates

47
00:02:01,080 --> 00:02:02,880
and the project's duration.

48
00:02:02,880 --> 00:02:05,520
The impact could be high as the departure

49
00:02:05,520 --> 00:02:08,370
of a key team member could lead to delays,

50
00:02:08,370 --> 00:02:11,190
increased cost, and potential quality issues.

51
00:02:11,190 --> 00:02:13,110
In this scenario, the project manager

52
00:02:13,110 --> 00:02:16,620
using qualitative risk analysis might prioritize the risk

53
00:02:16,620 --> 00:02:18,810
and develop mitigation strategies.

54
00:02:18,810 --> 00:02:21,330
These could include cross-training team members,

55
00:02:21,330 --> 00:02:23,880
documenting process and knowledge, and implementing

56
00:02:23,880 --> 00:02:27,060
a strong employee retention strategy.

57
00:02:27,060 --> 00:02:29,550
Another example would be in the construction industry.

58
00:02:29,550 --> 00:02:31,830
A potential risk in a skyscraper building project

59
00:02:31,830 --> 00:02:34,950
could be delayed in the delivery of critical materials.

60
00:02:34,950 --> 00:02:37,320
The likelihood of this risk could be assessed

61
00:02:37,320 --> 00:02:40,440
as high considering potential supply chain issues,

62
00:02:40,440 --> 00:02:43,320
vendor reliability, and external factors like weather

63
00:02:43,320 --> 00:02:45,240
or transportation disruptions.

64
00:02:45,240 --> 00:02:47,970
The impact will also be high as delays could lead

65
00:02:47,970 --> 00:02:50,490
to increased costs, scheduled overruns,

66
00:02:50,490 --> 00:02:52,860
and potential contractual issues.

67
00:02:52,860 --> 00:02:55,770
In this case, a project manager might prioritize the risk

68
00:02:55,770 --> 00:02:57,630
and develop mitigation strategies such

69
00:02:57,630 --> 00:03:00,780
as securing multiple vendors for critical materials,

70
00:03:00,780 --> 00:03:03,060
scheduling deliveries well in advance,

71
00:03:03,060 --> 00:03:06,630
and maintaining a buffer stock of essential materials.

72
00:03:06,630 --> 00:03:09,840
So remember, qualitative risk analysis is a method

73
00:03:09,840 --> 00:03:12,450
of assessing risk based on their potential impact

74
00:03:12,450 --> 00:03:14,850
and the likelihood of their occurrence.

75
00:03:14,850 --> 00:03:16,740
Likelihood refers to the probability

76
00:03:16,740 --> 00:03:19,800
or chance of a particular risk occurring.

77
00:03:19,800 --> 00:03:21,720
It is usually expressed qualitatively

78
00:03:21,720 --> 00:03:23,850
as low, medium or high.

79
00:03:23,850 --> 00:03:26,100
And finally, impact.

80
00:03:26,100 --> 00:03:28,530
Impact refers to potential consequences

81
00:03:28,530 --> 00:03:30,450
if the risk materializes.

82
00:03:30,450 --> 00:03:33,660
It could be in terms of cost, time, quality

83
00:03:33,660 --> 00:03:36,153
or other critical project objectives.

84
00:03:36,990 --> 00:03:38,220
Whatever industry you're in,

85
00:03:38,220 --> 00:03:41,370
effective risk analysis is key to navigating uncertainties

86
00:03:41,370 --> 00:03:43,743
and achieving project objectives.

